HomeMy WebLinkAbout10/22/2024 - Capital Projects Status Attachment AAttachment A: Status of Capital Projects
Board of Supervisors Work Session
October 22, 2024
Page 1 of 8
Recently Completed Projects
419 Corridor Design and Development
Planning
• The 419 Corridor Design and Development was funded $100,000 in FY 2022 for contract design
services to develop guidelines and update zoning regulations.
• The plan recommended new design principles for the planning area which could include adoption
and/or revision of new and existing ordinances as well as new development standards.
• The Office of Intermodal Planning and Investment (OIPI) provided technical assistance for the 419
Town Center Design Guidelines which were adopted in 2022.
Fire and Rescue Assessment
Fire & Rescue
• The assessment identified apparatus needs as facilities are updated, added or replaced. It also
helped County staff determine when, where, and what type of stations are needed to best serve
the citizens of Roanoke County and determine staffing needs.
• The assessment was funded $100,000 in FY 2023.
Fallowater Lane Extension
Planning
• The Fallowater Lane Extension project reconstructed an existing private commercial drive to
create a new public street to improve access for future development in the area designated as
“The Ridges” as recommended by the 419 Town Center Plan.
• The County administered the Preliminary Engineering and Construction phases, while VDOT
administered the Right-of-Way phase.
• The construction of the project was completed in 2023.
East Roanoke River Greenway at 3226 Highland Road
Parks, Recreation & Tourism
• The East Roanoke River Greenway project proposes to construct an approximate 6 miles of
greenways within Roanoke County’s Parks system between Roanoke City, the Blue Ridge
Parkway, and Explore Park.
• Funding in the amount of $250,000 was planned in FY 2024 as a local grant match for the Federal
Lands Access Program.
Voting Machine Replacement
Elections/Registrar
• The Voting Machine Replacement project replaced Roanoke County’s existing voting equipment
initially acquired in 2015. These machines will reach the end of their useful life within 10 years of
use.
• The project received $425,000 funding in FY 2024.
Attachment A: Status of Capital Projects
Board of Supervisors Work Session
October 22, 2024
Page 2 of 8
Mount Pleasant Library Improvements
Libraries and General Services
• In 2011, Roanoke County purchased the Mount Pleasant Library after leasing it for 2 years.
• Initially this project was funded in FY2019 to renovate the facility including updated restrooms,
windows, flooring, and upgrading shelving and furniture.
• Prior to beginning any design work for potential renovations for the building, the County initiated
a due diligence process to determine the feasibility of the septic and was determined that the
existing septic system has reached the end of its useful life
• The scope for additional improvements will be evaluated after addressing the necessary updates
to the library’s septic and sewer and new project will be created in future years at both the Mount
Pleasant and Bent Mountain Libraries, including various system upgrades.
Rural Broadband Initiative
Information Technology
• The Rural Broadband Initiative project improved communication and data technology in both the
business sector and in residential settings.
• The County collected survey data to identify areas where citizens either do not have or have
inadequate internet service. The survey results showed that more than 32% of Roanoke County
households in the targeted areas were considered unserved or under-served by the FCC's
minimum standards.
• Completed projects have brought high-speed Internet access to many residents and some
businesses.
Dynamics D365 Upgrade
Finance & Management Services
• The Dynamics D365 Upgrade Project upgraded the integrated financial system for the County,
Roanoke County Public Schools and the entities for whom the County serves as fiscal agent.
• The Finance Department went live with Microsoft Dynamics AX 2012 as the County’s integrated
financial system platform in July of 2016. Microsoft will no longer support the County’s current
platform starting in October 2021. This project focused on the upgrade of Dynamics AX 2012 to
the next generation of the Dynamics platform, D365.
Active Projects by Category
Assessments and Studies
New Zoning Ordinance
Planning
• Roanoke County’s current Zoning Ordinance was adopted in 1992, which included a
comprehensive rezoning of the County. Over the last 32 years, the Zoning Ordinance has been
amended on numerous occasions. A major overhaul of the ordinance is needed.
• The project proposes hiring a consultant to assist staff with developing new zoning ordinance.
• The project has funding from previous fiscal years of $200,000 and an additional $100,000 has
been added for FY2025.
Attachment A: Status of Capital Projects
Board of Supervisors Work Session
October 22, 2024
Page 3 of 8
Facilities Assessment
General Services
• This project is an update to the 2019 Facilities Conditions Assessment Study to update projects
based on current market conditions.
• Several critical building systems need replacement or repair, and the County is updating the Facility
Conditions assessment to prioritize future capital needs. This assessment also helps prioritize
projects in the capital maintenance programs.
Housing Study
Planning
• The Roanoke County Housing Plan will build upon the 2021 RKG Associates, Inc. Housing Study
and will include a residential market study for the County to identify issues and needed housing
alternatives now and in the future as well as recommendations to encourage development of these
needed housing alternatives.
• The project received $200,000 in funding in FY 2024.
• A Request for Proposals will be issued in late 2024.
East Roanoke River Greenway Feasibility Study
Planning
• The East Roanoke River Greenway Feasibility Study will consider alternative greenway alignments
proposed by the community at a June 2022 community meeting, as well as alignments included in
the 2003 East Roanoke River Greenway Master Plan.
• The segment of the Roanoke River Greenway proposed for the Feasibility Study is located
between the City of Roanoke and the Virginia Recreational Facilities Authority (VRFA) property
at 0 Eastland Road.
• The project received $200,000 in funding in FY 2024.
• AECOM has been selected to work on the study starting in Fall 2024.
Williamson/Peters Creek Road Multimodal Safety Study
Planning
• This project proposes to conduct a Multimodal Safety Study for portions of Williamson Road and
Peters Creek Road to develop at least one project to submit for grant funding.
• Continuing congestion, high profile crashes and significant development planned for this area
support the need for a multimodal safety study along portions of these roadways in the Hollins
area.
• The project received $200,000 in funding in FY 2024.
• The Virginia Department of Transportation (VDOT) funded and facilitated a similar study from
Peters Creek Road at Wood Haven Road to Williamson Road at Plantation Road in 2023 and
2024. The SMARTSCALE applications were submitted as a result of this study.
Attachment A: Status of Capital Projects
Board of Supervisors Work Session
October 22, 2024
Page 4 of 8
Buildings and Facilities
Hollins Library Replacement
Libraries and General Services
• The Hollins Library Replacement Project is slated to replace the existing Hollins Library, which is
the only major branch in the Roanoke County library system that has not been replaced.
• Planning and initial design is funded in FY23 ($200,000) and FY 2025 ($500,000).
• Construction is planned for bond funding in FY 2026.
Bonsack/460 Fire Station
Fire & Rescue
• The Bonsack/460 Fire Station was funded for $10.325 million in FY 2022 and FY 2023. This station
would represent a new and enhanced service as the twelfth station, which would reduce reliance
on other locality responses for emergencies. This station would replace services provided by the
Read Mountain Fire Station, now owned by Botetourt County, and would reduce the demand on
the City of Roanoke’s Station #14.
• In FY 2022, $1.0 million was funded with unrestricted cash for land acquisition and initial
architectural and engineering work. Bond funding, in the amount of $6.825 million and cash funding
in the amount of $2.5 million, was funded in FY 2023 to complete construction of the facility.
Public Service Center Facility Replacement
General Services
• The Public Service Center Facility Replacement Project began in FY 2017 with the completion of
a Building Planning Study.
• In FY 2018, County contracted for the acquisition of property to facilitate expansion of Fleet
Service Center. In FY 2019, Architectural and Engineering design services for Phase I were
contracted and commenced.
• Phase I includes expansion of the existing Fleet Services Center for all General Services
department functions, renovation of a section of the facility adjacent to the Fleet Service Center
for relocation of the Communications Shop and site management functions for Communications
& Information Technology, utilization of the existing site not located within the flood plain for
Stormwater Operations, and the relocation a district shop for the Parks, Recreation, and Tourism
Department to Green Hill Park.
• In FY 2020, the County purchased two additional properties on Hollins Road for the future
relocation of Parks, Recreation and Tourism offices and warehouse needs as Phase II of the
project. Phase II is currently underway.
Explore Park (Phase II)
Parks, Recreation & Tourism
• This project provides funds for the development of Explore Park infrastructure and
implementation of the Explore Park Adventure Plan. It provides the necessary park infrastructure
to support park operations for citizens and to market the facility for economic development.
• The first phase of the project completed water and sewer connections, design of internal park
water and sewer systems, design of the road system, bike skills park, building repairs, land studies,
broadband connections, land purchase, and road paving.
Attachment A: Status of Capital Projects
Board of Supervisors Work Session
October 22, 2024
Page 5 of 8
• Additional funding is planned in FY 2026 in the amount of $750,000 to expand parking capacity at
the park.
Jail Roof Replacement
Sheriff
• The Roanoke County Jail Roof Replacement is planned to replace the existing roof comprised of
a single-ply roof cover. Additionally, the concrete decks at each outdoor exercise area need to
be repaired and waterproofed.
• Replacement was allocated in FY 2024 ($135,000) and is planned in FY 2025 ($475,000) for a total
cost of $610,000.
• The cost of this project is shared with the City of Salem. ($17,550 in FY 2024 and $61,750 in FY
2025).
Courthouse HVAC Replacement
General Services
• The Courthouse HVAC Replacement project is planned to replace major HVAC components that
are original to the building, which have exceeded their useful life.
• Funding planned for FY 2025 to replace the chillers ($1,080,000).
• Funding in the amount of $5.1 million in FY 2027 is proposed to replace the rest of the HVAC
System.
Public Safety Center HVAC and UPS Replacements
General Services
• The Public Safety Center HVAC rooftop unit replacements are planned for an in-kind replacement
of the existing units.
• The Uninterrupted Power Supply (UPS) system is at the end of its useful life and needs to be
replaced with an in-kind system.
• The project received $2.05 million in funding in FY 2024.
Capital Maintenance Programs and Recurring Items
Roanoke County Broadband Authority – Debt Service
Economic Development
• The Roanoke Valley Broadband Authority (RVBA) has approximately 110 miles of network fiber
that traverses the region. Approximately 35 of those miles cross through Roanoke County and
serve our local organizations in healthcare, government, and non-profit sectors.
• Funding is proposed at $383,664 in FY 2025 and $768,647 in later years for the remaining debt
service payments.
Wood Haven Property Acquisition
Economic Development
• This project will create a 100+ acre business park, which will be owned and developed by the
Western Virginia Regional Industrial Facility Authority (WVRIFA).
Attachment A: Status of Capital Projects
Board of Supervisors Work Session
October 22, 2024
Page 6 of 8
• The project aims to increase the amount of marketable property in the Roanoke Valley available
for business development. The specific goal was to create new large parcels in the 50-100 acres
size range, due to consistent prospect interest in larger sites.
• Funding is proposed for $370,843 in FY 2025 and $2,962,943 in FY 2026 – FY 2033 for debt
service payments. Debt service payments are anticipated through FY 2037.
NDPES – Leachate Management System
Development Services
• This project funds the replacement of the existing leachate management system for the closed
Dixie Caverns Landfill.
• Obtaining a discharge permit from the DEQ is not financially feasible due to additional treatment
requirements. However, the WVWA has improved their downstream system, which has lessened
the need for an immediate system upgrade. Therefore, the County will continue to operate the
existing system with some minor upgrades to allow the ability for remote operation monitoring.
NPDES-MS4 BMP Construction
Development Services
• This program funds capital projects to improve water quality in streams to meet state
requirements.
• The department has applied and has been awarded a grant from the state Stormwater Local
Assistance Fund (SLAF) for the restoration of Wolf Creek, Phase II and Mudlick Creek.
• Funding in the amount of $1,010,850 in FY 2025 is combined with existing funds to meet the
County’s 50% share of grant funds.
Computer Infrastructure, Software and Hardware
Global HR: Human Resources and Payroll Modules (Phase I)
Human Resources and Finance & Management Services
• Roanoke County, Roanoke County Public Schools, and the Western Virginia Regional Jail began a
joint project in September of 2018 to implement Infor's Global Human Resources platform and
to migrate the existing Lawson payroll system to Infor's CloudSuite platform.
• Phase I of the project implemented the base HR system and integration of the HR system with
the Lawson payroll system. This phase provided employees with a new Employee Space employee
portal. Implementation for this phase occurred in March 2020.
• The COVID-19 pandemic delayed progress on Phase II to implement Performance and Goals and
Talent Acquisition.
Global Payroll Module (Phase II)
Finance & Management Services
• The Global Payroll project, replaces the current payroll system.
• Infor/Lawson CloudSuite Payroll will provide required platform changes and needed functionality.
• The project is proposed to receive $1.0 million in funding in FY 2024.
• Project costs are shared 50% with Roanoke County Public Schools.
Attachment A: Status of Capital Projects
Board of Supervisors Work Session
October 22, 2024
Page 7 of 8
Radio Systems RF Sites Generator Replacement
Emergency Communications
• This project will replace back-up generators at our RF Transmitter sites. Fort Lewis Mountain,
Poor Mountain and Crowell’s Gap.
• These generators are needed to maintain a reliable power source to the mountain top tower sites
to ensure uninterrupted service.
• The project is proposed to receive $120,000 in funding in FY 2024.
Genesis Operations Bridge
Emergency Communications
• This project will remove the email post office overload that has occurred at least 10 times over
the last several years causing catastrophic email failure in Roanoke County, which has prevented
the system from delivering alarm messages via email and SMS, text messages to key service &
management personnel.
• This equipment provides visualizations that quickly convey key information on the Public Safety
radio network to service personnel responsible for repair and maintenance of the public safety
network.
Enterprise GIS Maps and Apps Upgrade
Information Technology
• The Enterprise GIS Maps and Apps Upgrade project will upgrade the GIS Maps & Apps suite of
solutions used by the citizens and employees of the County of Roanoke.
• The current suite of applications is built on legacy technology and will not be supported into the
future, requiring the applications to be updated.
Email and Business Productivity Tools Replacement
Information Technology
• The County’s long-term email solution (Groupwise) and current business productivity solution
(desktop-based Microsoft Office) has been replaced with Microsoft Office 365.
• Additional funding is proposed for FY 2025 ($200,000) to finish implementation of the email and
business productivity tool replacement.
Transportation
Plantation Road, Phase II
Planning
• The Plantation Road Project Phase II continues pedestrian accommodations from the first phase
of the project with sidewalk, curb and gutter extending from the Walrond Drive intersection to
the Gander Way/Friendship Lane intersection. The Walrond Drive intersection was realigned and
pedestrian signals and crosswalks were added to the Plantation Road/Gander Way/Friendship
Lane traffic signal.
Attachment A: Status of Capital Projects
Board of Supervisors Work Session
October 22, 2024
Page 8 of 8
VDOT Revenue Sharing Program
Planning
• The Revenue Sharing Program provides additional funding for use by Roanoke County to
construct, reconstruct, improve, or maintain the VDOT secondary or primary highway system.
• Locality funds are matched with 50 percent state funds.
• Total program funding is proposed at $5.3 million over the ten-year plan, with $300,000 in FY
2025 designated for the Dry Hollow project.
Specialty Equipment
Replacement of Firearms
Police
• The Replacement of Firearms project replaces the department issued Glock 22/23s due to their
life cycle reaching the end of expectancy.
Emergency Medical Dispatch
Emergency Communications
• The Emergency Medical Dispatch project, funded in FY 2022 will upgrade the Emergency
Communications Center Medical Dispatch Program. The Emergency Medical Dispatch is a
systematic program of handling medical calls. Trained telecommunicators, using procedures
locally approved by the Operational Medical Director, quickly and properly determine the nature
and priority of the call, dispatch the appropriate response, then give the caller instructions to
help treat the patient until the responding Emergency Medical Services unit arrives.
• The current Emergency Medical Dispatch program was updated in 2006 and is out of date.