RESOLUTION 062698-1 TO ADVANCE FUNDS FOR CERTAIN
EXPENDITURES MADE AND/OR TO BE MADE IN CONNECTION WITH
THE ACQUISITION, RENOVATION, CONSTRUCTION AND EQUIPPING
OF CERTAIN CAPITAL IMPROVEMENTS FOR SCHOOL PROJECTS -
(CLEARBROOK ELEMENTARY SCHOOL)
WHEREAS, the Board of Supervisors of the County of Roanoke, Virginia (the
"County Board") adopted a resolution on August 19, 1997 declaring its intention to
reimburse itself from the proceeds of one or more tax-exempt financings for certain
expenditures made and/or to be made in connection with the acquisition, renovation,
construction and equipping of certain capital improvements for school projects, and
WHEREAS, the School Board (the "School Board") of the County of Roanoke,
Virginia (the "County") adopted a resolution on August 28, 1997 declaring its intention to
reimburse itself from the proceeds of one or more tax-exempt financings for certain
expenditures made and/or to be made in connection with the acquisition, renovation,
construction and equipping of certain capital improvements for school projects, and
WHEREAS, The School Board requested an advance of $ 50,000 on September
11, 1997 for environmental assessments, advertising costs for architects and engineers,
core drillings, and other costs related to the acquisition of land in South County, and
WHEREAS, the County Board approved this $50,000 advance on September 23,
1997, and
WHEREAS, the School Board requested an additional advance of $1,721,200 on
November 13, 1997 to hire architects to design various school projects, and
1
WHEREAS, the County Board approved this $1,721,200 additional advance on
November 18, 1997, and
WHEREAS, the School Board requested an additional advance of $130,000 on
November 13, 1997 to hire architects to begin renovations to the science labs, and
WHEREAS, the County Board approved a $104,000 additional advance on
December 16, 1997, and
WHEREAS, the School Board requested an additional advance of $200,000 to hire
contractors to begin a roof replacement program, and requested the amendment of Exhibit
A of County Resolution 081997-1 to appropriately reflect the roof replacement program
included in the Blue Ribbon Commission Report,
WHEREAS, the County Board approved this $200,000 additional advance on April
28, 1998, and the amendment to Exhibit A of County Resolution 081997-1, and
WHEREAS, the School Board has now requested an advance of funds to begin
construction at Clearbrook Elementary and Burlington Elementary,
NOW THEREFORE BE IT RESOLVED that the County Board will advance the
additional sum of $2,454,420 to the School Board for construction at Clearbrook
Elementary School.
On motion of Supervisor McNamara to adopt the resolution advancing funds for
Clearbrook Elementary School, and carried by the following recorded vote:
AYES: Supervisors McNamara, Harrison, Nickens, Johnson
NAYS: None
ABSENT: Supervisor Minnix
N
A COPY TESTE:
Mary H. Allen, CMC/AAE
Clerk to the Board of Supervisors
cc: File
Paul M. Mahoney, County Attorney
Diane D. Hyatt, Director, Finance
Dr. Deanna Gordon, School Superintendent
Brenda Chastain, Clerk, School Board
3
AT AN ADJOURNED MEETING OF THE BOARD OF SUPERVISORS OF ROANOKE
COUNTY, VIRGINIA, HELD AT THE ROANOKE COUNTY SCHOOL
ADMINISTRATION OFFICES ON TUESDAY, JUNE 26, 1998
RESOLUTION 062698-2 TO ADVANCE FUNDS FOR CERTAIN
EXPENDITURES MADE AND/OR TO BE MADE IN CONNECTION WITH
THE ACQUISITION, RENOVATION, CONSTRUCTION AND EQUIPPING
OF CERTAIN CAPITAL IMPROVEMENTS FOR SCHOOL PROJECTS -
(BONSACK ELEMENTARY SCHOOL)
WHEREAS, the Board of Supervisors of the County of Roanoke, Virginia (the
"County Board") adopted a resolution on August 19, 1997 declaring its intention to
reimburse itself from the proceeds of one or more tax-exempt financings for certain
expenditures made and/or to be made in connection with the acquisition, renovation,
construction and equipping of certain capital improvements for school projects, and
WHEREAS, the School Board (the "School Board") of the County of Roanoke,
Virginia (the "County") adopted a resolution on August 28, 1997 declaring its intention to
reimburse itself from the proceeds of one or more tax-exempt financings for certain
expenditures made and/or to be made in connection with the acquisition, renovation,
construction and equipping of certain capital improvements for school projects, and
WHEREAS, The School Board requested an advance of $ 50,000 on September
11, 1997 for environmental assessments, advertising costs for architects and engineers,
core drillings, and other costs related to the acquisition of land in South County, and
WHEREAS, the County Board approved this $50,000 advance on September 23,
1997, and
WHEREAS, the School Board requested an additional advance of $1,721,200 on
November 13, 1997 to hire architects to design various school projects, and
1
WHEREAS, the County Board approved this $1,721,200 additional advance on
November 18, 1997, and
WHEREAS, the School Board requested an additional advance of $130,000 on
November 13, 1997 to hire architects to begin renovations to the science labs, and
WHEREAS, the County Board approved a $104,000 additional advance on
December 16, 1997, and
WHEREAS, the School Board requested an additional advance of $200,000 on
March 26, 1998 to hire contractors to begin a roof replacement program, and requested
the amendment of Exhibit A of County Resolution 081997-1 to appropriately reflect the roof
replacement program included in the Blue Ribbon Commission Report,
WHEREAS, the County Board approved this $200,000 additional advance on April
28, 1998, and the amendment to Exhibit A of County Resolution 081997-1, and
WHEREAS, the School Board requested additional advances of $2,454,420 to
begin construction at Clearbrook Elementary and $2,517,100 to begin construction at
Burlington Elementary on May 14, 1998, and
WHEREAS, the School Board has now requested an additional advance of
$7,213,520 to begin construction at Bonsack Elementary School.
NOW THEREFORE BE IT RESOLVED that the County Board will advance the
additional sum of $7,213,520 to the School Board for construction at Bonsack Elementary
School.
On motion of Supervisor Johnson to adopt the resolution advancing funds for
Bonsack Elementary School, and carried by the following recorded vote:
2
AYES: Supervisors McNamara, Harrison, Nickens, Johnson
NAYS: None
ABSENT: Supervisor Minnix
A COPY TESTE:
Mary H. Allen, CMC/AAE
Clerk to the Board of Supervisors
cc: File
Paul M. Mahoney, County Attorney
Diane D. Hyatt, Director, Finance
Dr. Deanna Gordon, School Superintendent
Brenda Chastain, Clerk, School Board
AT AN ADJOURNED MEETING OF THE BOARD
OANOKE
COUNTY, VIRGINIA, HELD AT THE ROANOKE COUNTY SCHOOL
ADMINISTRATION OFFICES ON TUESDAY, JUNE 26, 1998
RESOLUTION 062698-3 TO ADVANCE FUNDS FOR CERTAIN
EXPENDITURES MADE AND/OR TO BE MADE IN CONNECTION WITH
THE ACQUISITION, RENOVATION, CONSTRUCTION AND EQUIPPING
OF CERTAIN CAPITAL IMPROVEMENTS FOR SCHOOL PROJECTS -
(BURLINGTON ELEMENTARY SCHOOL)
WHEREAS, the Board of Supervisors of the County of Roanoke, Virginia (the
"County Board") adopted a resolution on August 19, 1997 declaring its intention to
reimburse itself from the proceeds of one or more tax-exempt financings for certain
expenditures made and/or to be made in connection with the acquisition, renovation,
construction and equipping of certain capital improvements for school projects, and
WHEREAS, the School Board (the "School Board") of the County of Roanoke,
Virginia (the "County") adopted a resolution on August 28, 1997 declaring its intention to
reimburse itself from the proceeds of one or more tax-exempt financings for certain
expenditures made and/or to be made in connection with the acquisition, renovation,
construction and equipping of certain capital improvements for school projects, and
WHEREAS, The School Board requested an advance of $ 50,000 on September
11, 1997 for environmental assessments, advertising costs for architects and engineers,
core drillings, and other costs related to the acquisition of land in South County, and
WHEREAS, the County Board approved this $50,000 advance on September 23,
1997, and
WHEREAS, the School Board requested an additional advance of $1,721,200 on
November 13, 1997 to hire architects to design various school projects, and
1
WHEREAS, the County Board approved this $1,721,200 additional advance on
November 18, 1997, and
WHEREAS, the School Board requested an additional advance of $130,000 on
November 13, 1997 to hire architects to begin renovations to the science labs, and
WHEREAS, the County Board approved a $104,000 additional advance on
December 16, 1997, and
WHEREAS, the School Board requested an additional advance of $200,000 to hire
contractors to begin a roof replacement program, and requested the amendment of Exhibit
A of County Resolution 081997-1 to appropriately reflect the roof replacement program
included in the Blue Ribbon Commission Report,
WHEREAS, the County Board approved this $200,000 additional advance on April
28, 1998, and the amendment to Exhibit A of County Resolution 081997-1, and
WHEREAS, the School Board has now requested an advance of funds to begin
construction at Clearbrook Elementary and Burlington Elementary,
NOW THEREFORE BE IT RESOLVED that the County board will advance the
additional sum of $2,517,100 to the School Board for construction at Burlington
Elementary School.
On motion of Supervisor Johnson to adopt the resolution advancing funds for
Burlington Elementary School, and carried by the following recorded vote:
AYES: Supervisors McNamara, Harrison, Nickens, Johnson
NAYS: None
ABSENT: Supervisor Minnix
2
A COPY TESTE:
Mary H. Allen, CMC/AAE
Clerk to the Board of Supervisors
cc: File
Paul M. Mahoney, County Attorney
Diane D. Hyatt, Director, Finance
Dr. Deanna Gordon, School Superintendent
Brenda Chastain, Clerk, School Board